Housing Project at the Weizmann Institute of
Science
Report of the meeting the ``vaadat higui''.
Thursday, October 14
Present: Niki, Yonathan, Gad Kober
Israel Bar-Yosef, Aldo Shemesh, Amnon Horowitz, Daniel Zajfman,
Eliezer Ronen
- A short report was given by Gad on the overall schedule of the
project. There is again a delay caused by the fact that the city of
Rehovot has not yet taken a decision on the project. The next meeting
of the City Committee is scheduled to be on November 10, and it is
hoped that at that point we will received a positive
answer. Basically, from now on, this is what makes the whole project
standing still.
- Accoring to the point above, a new schedule was set up. Based on
this schedule, and if the city of Rehovot gives his agreement, the
infrastructure work should start by the end of November. This is
linked to the condition that we sign the contract with the Institute.
- The whole infrastructure plan (Pituach) of the twon is basically ready. We
plan to have a meeting next week where the exact location of each
houses, stairs, alleys, fences, trash, electricity and communication
boxes will be shown.
- The constructor is working on the basic houses (``typussim'')
construction, and we hope that by January, every one of us will get
the final plan (scale 1/50) of the house, were details (electricity
etc..) will be dealt with. THUS, WE URGE EVERYBODY, AND SPECIALLY
THOSE WHO HAVE NOT YET STARTED (!) TO GET IN TOUCH WITH YOUR ARCHITECT
AND/OR NIKI ASAP! Plans must be finalize so that the architects and
the constructor will not have to go back and forth with your corrections.
It takes months for the main architect of the project to convert your plan to
working plans, so we should all have these handy and ready.
- As part of the previous point, we would like to stress that
everybody should check the size of the house. There has been some
disagreement betwen the value given by the different architects, and
everybody should check that the numbers are correct.